- Govern each part of the project by its nature. What only shows up in the system is built iteratively; what must work on a cutoff date follows a plan.
- PRINCE2® provides management stages, tolerances, and the project board. SAFe® provides joint planning of several teams on a fixed cadence.
- WSJF ranks enhancement requests by cost of delay relative to size. Legal requirements and anything critical for go-live sit outside this ranking.
- Before the start, clarify who prioritizes, who approves data, and who decides on tolerances.
Why “agile versus waterfall” is the wrong question
The “agile versus waterfall” debate comes from software development. An ERP project is more than development. It changes processes, migrates years of data, and switches operations over on a fixed date.
These parts behave differently. Govern them all the same way, and you make either the migration unpredictable or the process design cumbersome.
How to govern each part
| Project part | Characteristic | Governance | Warning sign |
|---|---|---|---|
| Process design | Gaps only show up in the system | Cycles of workshop, system demo, and adjustment | Design documents wait weeks for approval |
| Enhancements and custom software | Requirements change during the project | Backlog, sprints, review with the business | The specification is outdated before development starts |
| Reports and analytics | The value only shows with real data | Short cycles with key users | Reports go unused after go-live |
| Data migration | Quality comes from repetition | Test migrations (mock migrations) on a fixed cadence, reconciliation after every run | Each test migration runs differently from the last |
| Cutover | Fixed date, fixed sequence | Runbook with go/no-go decision, see cutover runbook | On Sunday evening, people debate what “done” means |
| Contracts and contract award | The scope of services must be specified up front | Fixed framework with defined flexibility, for example a budget allowance for enhancements | Every change becomes a change request |
Data migration is a special case. It runs in cycles, but with fixed requirements. Every test migration follows the same procedure so that the results are comparable.
The framework: PRINCE2® for decisions, SAFe® for cadence
In practice, a division of labor between the methods works well. Each level answers a different question.
| Level | Method | Contribution | Who decides |
|---|---|---|---|
| Executive management | PRINCE2® | Management stages with a decision at every stage boundary, tolerances, management by exception | Project board |
| Several teams | Elements of SAFe® | Joint planning on a fixed cadence (PI Planning), visible dependencies between teams | Project lead with the product owners |
| Team | Scrum or Kanban | Short cycles, prioritized backlog, regular demos | Product owner in the business |
| Migration and cutover | Plan-driven | Scheduled test migrations, runbook, go/no-go | Project board, on the project lead’s recommendation |
The project board, called the steering committee in many companies, decides at the stage boundaries. The management stages follow the milestones of migration and cutover, and the teams deliver toward these milestones at their own cadence. Our five project phases follow the same pattern.
Tolerances also differ by part. PRINCE2® 7 defines tolerances for time, cost, scope, quality, risk, benefits, and sustainability. Agile teams get leeway on scope, while migration and cutover get a tight tolerance on the date.
Prioritizing with WSJF
When there are more enhancement requests than capacity, a transparent ranking helps. SAFe® uses Weighted Shortest Job First (WSJF) for this: the cost of delay of an item is divided by its duration. Because duration is hard to estimate, teams use relative size in practice.
Cost of delay is made up of three values, each estimated relative to the other items. They are user and business value, time criticality, and risk reduction or opportunity enablement. A modified Fibonacci sequence is common for the estimates (1, 2, 3, 5, 8, 13, 20).
Here is a worked example with assumed values from an ERP backlog. Cost of delay is shown as the sum of value, time criticality, and risk reduction or opportunity enablement.
| Item | Cost of delay | Size | WSJF |
|---|---|---|---|
| Add supplier and planned delivery time to the MRP list | 8 + 5 + 3 = 16 | 3 | 5.33 |
| Determine the source of supply automatically via source list and purchasing info records | 13 + 8 + 5 = 26 | 8 | 3.25 |
| New layout for the delivery note | 3 + 2 + 1 = 6 | 2 | 3.00 |
| Interface to an additional shipping provider | 8 + 13 + 8 = 29 | 13 | 2.23 |
The small MRP list enhancement comes first, even though automatic source determination brings more value. It delivers value quickly and ties up little capacity. If the new interface must be live at go-live, it does not belong in this ranking at all.
This is where WSJF reaches its limit. Legal requirements and everything that go-live depends on come before any prioritization. WSJF orders the rest, and it is only as good as the joint estimate of business and IT.
Separate the roles clearly
Clarify before the start who decides what. This is how we split the roles when we hold overall project leadership:
- The project lead owns plan, budget, and milestones. They alert the project board when a tolerance is forecast to be exceeded.
- The product owners in the business own the content and priority of their backlog. For that, they need decision-making authority.
- The data owners for each area own cleansing, reconciliation, and sign-off of their migration objects.
- Under PRINCE2®, the project board represents business, user, and supplier interests. It decides at the stage boundaries and whenever a tolerance is exceeded.
Typical mistakes in hybrid projects
- “Agile” serves as an excuse for a lack of planning in migration and cutover.
- Sprints have no link to the management stages. Team deliveries miss the milestones.
- Product owners lack decision-making authority, and every priority is renegotiated by the project board.
- A fixed price applies to a scope that is meant to change iteratively.
- The project board decides details instead of deviations from the tolerances.